Accepted-Output Calculator
Turn a nominal kg/h row into a testable planning number by applying scheduled hours, availability and first-pass accepted yield.
612 kg/shift
100 × 8 × 85% × 90% = 612
Use the estimate in a factory acceptance test
Define the reference recipe, bead diameter, start/stop rule, sampling interval, leakage or broken-membrane reject criteria, test duration and the exact point where accepted kilograms are weighed. Record changeover and sanitation time separately.
This calculator is a planning model, not a machine guarantee. Availability and accepted yield must come from your agreed test protocol, not from a generic assumption.